How to Track Crew and Man-Days by Trade on Site
Short answer: record headcount per trade every day with a shift value (1 = full day), multiply to get man-days, and add the days up per site and month.
1. Count by trade, not just heads
"12 workers" says little. "Carpenters 5, rebar 4, laborers 3" tells you where the hours went and who to pay.
2. Use one shift rule
Full day = 1, half day = 0.5, long day = 1.5. Write the rule down once and use it every day.
3. Record stopped days too
Rain, a late pump, an inspection hold — mark the day stopped or half day and keep the report.
4. Add it up per site
At the end of the month, total man-days per trade per site. That is the number everyone asks for at payday.
How Brickjot helps
Each trade is one row with big + and − buttons and 0.5 / 1 / 1.5 chips. The report header shows total workers and man-days. On the Sites tab, each site shows man-days by trade for this month, last month or all time, plus days stopped, and Share totals sends it as text.
FAQ
What is a man-day?
One worker for one full working day. Two workers for half a day is also one man-day.
How do I count overtime?
Use a shift value above 1, for example 1.5 for a long day, and keep the same rule for the whole site.
How do I count days lost to rain?
Mark the day as work stopped and record zero or partial crew. Keep the report anyway — stopped days matter at claim time.